Question: Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for
Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for project i = 1,...,5. Write the appropriate constraint(s) for each condition. Conditions are independent.
a. Choose no fewer than three projects.
b. If project 3 is chosen, project 4 must be chosen. If project 3 is not chosen, then we have the option to choose or not choose project 4.
c. If project 1 is chosen, project 5 must not be chosen.
d. Projects cost 100, 200, 150, 75, and 300 respectively. The budget is 450.
e. No more than two of projects 1, 2, and 3 can be chosen.
Step by Step Solution