Question: Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for

Consider a capital budgeting example with five projects from which to select. Let xi =1 if project i is selected, 0 if not, for i =1,...,5. Write the appropriate constraint(s) for each condition. Conditions are independent. (a) Choose no fewer than four projects.
(b) If project 1 is chosen, project 5 must be chosen.
(c) If project 3 is chosen, project 4 must not be chosen.
(d) Projects cost 100,200,150,75, and 300, respectively. The budget is 450.
(e) No more than two of projects 2,3, and 4 can be chosen.
 Consider a capital budgeting example with five projects from which to