Question: Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for
Consider a capital budgeting example with five projects from which to select. Let xi if project i is selected, if not, for i Write the appropriate constraints for each condition. Conditions are independent. a Choose no fewer than four projects.
b If project is chosen, project must be chosen.
c If project is chosen, project must not be chosen.
d Projects cost and respectively. The budget is
e No more than two of projects and can be chosen.