Question: Consider a five - step process to assemble overhead projectors. The base of the projector is assembled in Step 3 and the lamp assembly is

Consider a five-step process to assemble overhead projectors. The base of the projector is assembled in Step 3 and the lamp assembly is done in Step 4. The base assembly takes inputs from Steps 1 and 2 where the two subassemblies for the same unit are worked upon simultaneously. Similarly in steps 3 and 4 the subassemblies for the same unit are simultaneously worked upon. The base and the lamp subassemblies are combined in Step 5 to assemble the overhead projector. There is one worker at each step, and the entire process operates for 480 min/day.
Now suppose Step 6- Final Inspection, which takes 21 min per unit, is added after Step 5. There are two workers assigned at Step 6. Which of the following statement is TRUE?
Question 34 options:
a)
The capacity and minimum flow time will stay the same
b)
The capacity will stay the same but the cycle time will increase
c)
The capacity will stay the same but the minimum flow time will increase
d)
Both capacity and cycle time will decrease

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!