Question: Consider a four-step serial process with the number of workers at each step and processing times given in the list below. Process Step Number of
| Consider a four-step serial process with the number of workers at each step and processing times given in the list below. | ||||
| Process Step | Number of Workers | Time per Customer (in Minutes) | ||
| 1 | 1 | 7 | ||
| 2 | 3 | 16 | ||
| 3 | 3 | 8 | ||
| 4 | 3 | 5 | ||
| Assuming that the process starts out empty and is worker-paced, how long will it take (in minutes) to serve 26 customers? (Round to nearest minute) | ||||
At a car wash, services offered include vacuum, wash and detail. The vacuum process has a demand of 13 customers per hour. The wash process has demand of 8 customers per hour. The detail process has a demand of 14 customers per hour. There are 3 employees staffing the vacuum process and each has a capacity of 10 customers per hour. The wash process is staffed by 3 employees, who can each serve 5 customers per hour. The detail is performed by 4 employees, each of whom can serve 6 customers per hour.
what is implied utilization?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock