Question: Consider a M / M / 3 queuing system where all notations follow standard Kendell s notation. Assume number of customers arriving in the queue

Consider a M/M/3 queuing system where all notations follow standard Kendells notation. Assume number of customers arriving in the queue at a rate of 40 per hour and the time taken by each server to serve a customer is 3 minutes. What can be the value of the utilization factor (P)?