Question: consider a machine that processes two different parts, each A part requires 20 sec of work, and each Part B requires 10 sec of work.
consider a machine that processes two different parts, each A part requires 20 sec of work, and each Part B requires 10 sec of work. The machine needs a setup time of 40 min while changing from A to B , and 45 min while changing from B to A. Both parts are feeding an assembly line for the final product . for each product 2 parts of A and 3 Parts of B. Assume that the batch sizes of A and B are chosen togther and batch size of B is 1.5 times the batch of A.
a. If the batch size for A is 600, will this be enough to feed an assembly line with a rate of 20 per hour?
b. what should be the minimum batch size of part A if production rate increased to 40 per hour?
c. Consider the rates and batch size on part a. what percent of time the machine is idle ?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock