Question: Consider a manufacturing process depicted by the following flowchart. Station A has 3 parallel operators, A1, A2, and A3. Station C has 2 parallel opertors,

Consider a manufacturing process depicted by the following flowchart. Station A has 3 parallel operators, A1, A2, and A3. Station C has 2 parallel opertors, C1 and C2. Each unit only needs to be processed by one of the operators A1,A2 and A3. After being processed at Station B, a unit then needs to be processed by either C1 or C2. The process time of the individual operators are given as follows. Each of A1,A2, and A3:10 minutes B: 14 minutes Either of C1 and C2:1 minutes. What is the process time (in minutes) of the whole process? Round your final answer to 2 decimal places if it is not a whole number