Question: Consider a milling machine is needed to make 200 steer support, 400 ribs per Xootr, and 200 frame as a batch for 200 products (the
Consider a milling machine is needed to make 200 steer support, 400 ribs per Xootr, and 200 frame as a batch for 200 products (the batch size). What is the process capacity?

Please follow the following steps:
- Step 1. Define the batch component set
- Step 2. Define the batch size
- Step 3: Find the setup time
- Step 4: Find the processing time for each component set
- Step 5: Find the Process Capacity following the equation.
\begin{tabular}{|l|l|l|} \hline & Setuptime(min) & Processingtime(min) \\ \hline Steer support & 40 & 1.5 \\ \hline Rib & 45 & 0.6 \\ \hline Frame & 30 & 2 \\ \hline \end{tabular}