Question: Consider a process consisting of four resources: Resource Activity Time [Min./Unit] Number of Workers 1 5 2 2 4 1 3 16 4 4 6

Consider a process consisting of four resources: Resource Activity Time [Min./Unit] Number of Workers 1 5 2 2 4 1 3 16 4 4 6 3 If the demand is 12 units per hour what is the flow rate of this process?

Question 14 options: 12 10 30 15 24