Question: Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are always performed in the following
Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are always performed in the following sequence.
- Resource 1 has a processing time of 7 minutes per unit.
- Resource 2 has a processing time of 4 minutes per unit.
- Resource 3 has a processing time of 6 minutes per unit.
All three resources are staffed by one worker and each worker gets paid $10 per hour.