Question: Consider a process consisting of three resources. Each resource is staffed by two workers. Assume the demand rate is 1 0 units per hour. -

Consider a process consisting of three resources. Each resource is staffed by two workers. Assume
the demand rate is 10 units per hour.
- Resource 1 has a processing time of 10 minutes per unit.
- Resource 2 has a processing time of 8 minutes per unit.
- Resource 3 has a processing time of 6 minutes per unit.
(a) What is the idea cycle time to meet the demand? (15/100)
(b) Assume the workers are paid $20 per hour. Each unit is sold for $20 and includes parts that are
sourced for $5. The company has utility costs of $10 per hour. What would be the profits per hour if
they were able to reduce the processing time at the bottleneck by 30%?(20/100)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!