Question: Consider a process consisting of three resources. Each resource is staffed by one worker. Assume the demand rate is 10 units per hour. Resource #1

Consider a process consisting of three resources.Consider a process consisting of three resources.

Consider a process consisting of three resources. Each resource is staffed by one worker. Assume the demand rate is 10 units per hour. Resource #1 has a processing time of 5 minutes per unit. Resource #2 has a processing time of 4 minutes per unit. Resource #3 has a processing time of 2 minutes per unit. 6. What would be the flow rate of the process if they were able to reduce the processing time at the bottleneck by 30%? (20 points)