Question: Consider a process consisting of three resources: table [ [ Resource , Processing Time [ Min . / Unit ] , Number of Workers
Consider a process consisting of three resources:
tableResourceProcessing Time MinUnitNumber of Workers
where the existence of the number of workers at each resourcestation means they are working in parallel.
What is the bottleneck?
What is the process capacity?
What is the flow rate if demand is eight units per hour?
What is the utilization of each resource if demand is eight units per hour?