Question: Consider a process consisting of three steps conducted sequentially, and each step is staffed by one worker. Assume there exists unlimited demand for the product.

Consider a process consisting of three steps conducted sequentially, and each step is staffed by one worker. Assume there exists unlimited demand for the product.
Resource 1 has a processing time of 6 minutes per unit.
Resource 2 has a processing time of 3 minutes per unit.
Resource 3 has a processing time of 5 minutes per unit.
What is the utilization of resource 2?
The utilization of resource 2 is percent.