Question: Consider a process consisting of ve steps that must be performed in sequence with no waiting between steps. That is, perform task A rst, followed


Consider a process consisting of ve steps that must be performed in sequence with no waiting between steps. That is, perform task A rst, followed by B, and so on in alphabetical order. The task requirements and resource allocations for these tasks are in the following table. Activity time for a single worker # of workers (min/unit) The manager of this process would like to analyze the current conguration and identify opportunities for improvement. To help him, answer the following. (Fill out with numbers only, keep three digits after the decimal if not whole numbers): What is the bottleneck?(Fill out with letter in this problem) What is the capacity of this process? What is the ow time in mins? What is the cycle time in mins