Question: Consider a process that has 3 stations, ordered in sequence: A , B and C . At each station, two consecutive tasks are performed one

Consider a process that has 3 stations, ordered in sequence: A, B and C. At each station, two consecutive tasks are performed one after the other. The time (in seconds per unit) it takes for a single person to perform each task is given in the table below (e.g., task A2 takes 10 seconds per unit):
Station
# of
Workers
Task
A1
Task
A2
Task
B1
Task
B2
Task
C1
Task
C2
A
1
20
10
-
-
-
-
B
2
-
-
40
40
-
-
C
1
-
-
-
-
15
5
The table also gives the number of workers at each station. There is ample buffer capacity between each station. What is the capacity of this process (in units per minute)?
Question 2 options:
2
2.5
3
1.5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!