Question: Consider a process with three serial tasks - Station 1, Station 2 and Station 3 where Station 2 is the bottleneck. By reducing the activity
Consider a process with three serial tasks - Station 1, Station 2 and Station 3 where Station 2 is the bottleneck. By reducing the activity or task time at Station 1 (choose the best answer):
capacity of the process will increase and flow time of process will decrease
capacity of the process will decrease and flow time of process will increase
capacity of the process will be unchanged and flow time will decrease
both capacity of the process and flow time of process will be unchanged
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock