Question: Consider a project activity that has an optimistic time of 3 weeks, a most likely time of 10 weeks, and a pessimistic time of 25
Consider a project activity that has an optimistic time of 3 weeks, a most likely time of 10 weeks, and a pessimistic time of 25 weeks. What is the expected time for that activity?
(Round answer to 2 decimal places, e.g. $52.50.)
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
Step 11 Given Optimistic Time t 3 weeks Most likely time tm 10 weeks Pessi... View full answer