Question: Consider a project consisting of 6 activities (A,B,C,D,E,F) with the following precedence relations and time estimates. (i) Construct an activity - on arc network for

Consider a project consisting of 6 activities (A,B,C,D,E,F) with the following precedence relations and time estimates.

Consider a project consisting of 6 activities

(i) Construct an activity - on arc network for the project.

(ii) Determine the Earliest start (ES), the late start, the total float for each activity.

(iii) List the activities on the critical path, and what is the earliest project completion time.

\begin{tabular}{|c|c|c|} \hline Activity & Immediate Predecessors & Duration (Days) \\ \hlineA & & 5 \\ \hlineB & A & 8 \\ \hlineC & B & 10 \\ \hlineD & B & 5 \\ \hlineE & D & 4 \\ \hlineF & C,E & 3 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!