Question: Consider a project having the following seven activities: Activity Time (weeks) Immediate predecessors none A B D E F G none A A B DE

Consider a project having the following seven
Consider a project having the following seven activities: Activity Time (weeks) Immediate predecessors none A B D E F G none A A B DE F 4 6 9 7 4 5 4 a) What is the critical time? (2 marks) b) What is the critical path? (2 marks)