Question: Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B
Consider a project having the following six activities:
Immediate Max Crash cost
Activity Predecessors Time (weeks) Crash* per week
A none 6 6 N/A
B none 5 2 $500
C A 3 2 $1000
D A, B 4 2 $2000
E C, D 5 2 $1250
F D 4 2 $1000
*Shortest possible time for the task
- Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task
- List the tasks on the critical path
- What is the expected project duration in weeks?
- What is the slack for each activity?
A: B: C: D: E: F:
- The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2 week crash at lowest cost? List the new duration of each task and any associated crash costs (0.5 pts.)
Activity Duration Crash Cost
A
B
C
D
E
F
- Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task (0.6 pts.)
- List the tasks on the critical path (0.4 pts.)