Question: Consider a project lasting one year which costs X in year zero and generates a cash flow of Y in year one. The project has
Consider a project lasting one year which costs X in year zero and generates a cash flow of Y in year one. The project has an internal rate of return of 10%. This means that
- If the appropriate market interest rate is less than 10%, then the project has a negative NPV
- The NPV of the project is X-Y/1.1
- If the appropriate market interest rate is greater than 10%, then the project has a positive NPV
- If the appropriate market interest rate is greater than 10%, then the project has a negative NPV
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
