Question: Consider a project that has been analyzed using CPM-PERT, and now we have all information about the critical path, the project completion time and its
Consider a project that has been analyzed using CPM-PERT, and now we have all information about the critical path, the project completion time and its distribution. Suppose we know that the project completion time,
Tp~Tp~
(56, 18), where the time units are in days. Suppose you are a contractor and have a serice policy of 90%. If you are going to bid for a project and propose a time that meets your service policy, what is the maximimum Tp you will include your bid? Please ROUND your answer to the NEAREST INTEGER.