Question: Consider a project that has been modeled as follows: Activity Pre - acti Optimistic ( wks ) Most Likely Pessimistic A None 9 1 5

Consider a project that has been modeled as follows:
Activity Pre-acti Optimistic(wks) Most Likely Pessimistic
A None 91521
B None 132123
C A 6918
D B 233547
E A,D 192627
F C 232941
G D, E 142026
H E, F, G 258
Determine project's expected completion time and its critical path.
Answer: Critical Path______________________________
Expected completion time_____________________
What is the probability that the project will complete more than 27 weeks?