Question: Consider a project that has been modeled as follows: Activity Pre - acti Optimistic ( wks ) Most Likely Pessimistic A None 9 1 5
Consider a project that has been modeled as follows:
Activity Preacti Optimisticwks Most Likely Pessimistic
A None
B None
C A
D B
E AD
F C
G D E
H E F G
Determine project's expected completion time and its critical path.
Answer: Critical Path
Expected completion time
What is the probability that the project will complete more than weeks?
Step by Step Solution