Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Duration (hr) A --- 7 B --- 10 C A 4 D A
Consider a project that has been modeled as follows:
| Activity | Immediate Predecessors | Duration (hr) |
| A | --- | 7 |
| B | --- | 10 |
| C | A | 4 |
| D | A | 30 |
| E | A | 7 |
| F | B,C | 12 |
| G | C | 15 |
| H | E,F | 11 |
| I | E,F | 25 |
| J | F | 6 |
| K | D,H | 21 |
| L | G,J | 25 |
| Determine project's expected completion time and its critical path.
Answer: Critical Path______________________________
Expected completion time_____________________ |