Consider a project that has been modeled as follows: Activity Immediate Predecessors Duration (hr) A --- 7
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider a project that has been modeled as follows:
Activity | Immediate Predecessors | Duration (hr) |
A | --- | 7 |
B | --- | 10 |
C | A | 4 |
D | A | 30 |
E | A | 7 |
F | B,C | 12 |
G | B,C | 15 |
H | E,F | 11 |
I | E,F | 25 |
J | E,F | 6 |
K | D,H | 21 |
L | G,J | 25 |
a. | Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path. |
b. | Can activities E and G be performed simultaneously without delaying the minimum project completion time? |
c. | Can one person perform A, G, and I without delaying the project? |
d. | By how much can activities G and L be delayed without delaying the entire project? |
e. | How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain. |