Question: Consider a project whose activities are listed in the table below. In order to ensure that the project is completed on time, Activity B must
Consider a project whose activities are listed in the table below. In order to ensure that the project is completed on time, Activity B must start, at the latest, by time
| Activity | Immediate Predecessors | Duration |
| A | None | 10 |
| B | None | 2 |
| C | B | 2 |
| D | C | 2 |
| E | D | 2 |
| F | A, E | 4 |
| G | F | 4 |
| a. | 0 | |
| b. | 1 | |
| c. | 2 | |
| d. | 3 |