Question: Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec
Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec task is supposed to be 60% complete but actual percent completed is 40%. The actual cost of the task A is $4000.
Calculate the following:
- Schedule Variance
- Schedule Performance Index
- Cost Variance
- Cost Performance Index
Step by Step Solution
3.42 Rating (149 Votes )
There are 3 Steps involved in it
To calculate the Schedule Variance SV we can use the formula SV Earned Value EV Planned Value PV whe... View full answer