Question: Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec

Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec task is supposed to be 60% complete but actual percent completed is 40%. The actual cost of the task A is $4000. 

Calculate the following: 

- Schedule Variance 

- Schedule Performance Index 

- Cost Variance 

- Cost Performance Index

Step by Step Solution

3.42 Rating (149 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the Schedule Variance SV we can use the formula SV Earned Value EV Planned Value PV whe... View full answer