Question: Consider a project with the following activity list. How many activities are critical? (In a critical activity, early start is equal to late start) Activity

Consider a project with the following activity list. How many activities are critical? (In a critical activity, early start is equal to late start)

Activity Predecessor Duration A - 5 B A 7 C A 3 D C 5 E A 4 F E 4 G B,D,F 2 H G 5

Group of answer choices

7

5

6

8