Question: Consider a project with the following activity list. How many activities are critical? (In a critical activity, early start is equal to late start) Activity
Consider a project with the following activity list. How many activities are critical? (In a critical activity, early start is equal to late start)
Activity Predecessor Duration A - 5 B A 7 C A 3 D C 5 E A 4 F E 4 G B,D,F 2 H G 5
Group of answer choices
7
5
6
8