Question: Consider a project with the following cash flows: CF0 = -$600, CF1 = $1,110, CF2 = $700, CF3 = -$600, and CF4 = -$1, 200.
Consider a project with the following cash flows: CF0 = -$600, CF1 = $1,110, CF2 = $700, CF3 = -$600, and CF4 = -$1, 200. Use Excel to answer the following questions:
(a) Plot the project's NPV as a function of the discount rate r
(b) Calculate the internal rate of return of this investment opportunity. Would you pursue this project if the opportunity cost of capital is 10%? 50%? 60%?
(c) Calculate the NPV of this investment opportunity under discount rate of 12%. Would you accept this project based on the NPV rule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
