Question: Consider a simple project in which four activities describe the basic tasks. This project is presented as a bar chart drawn as a timescaled schedule.
Consider a simple project in which four activities describe the basic tasks. This project is presented as a bar chart drawn as a timescaled schedule. The sum of the amounts for the activities in the schedule of values approximates the originally anticipated cost of the project. The project duration is five weeks. After three weeks, Activity A is 100% complete, and its total cost is $900; Activity B is 40% complete, and its cost to date is $1,400; Activity D is 50% complete, and its cost to date is 1,500. Complete the following table to answer the questions below. Activity Budget Cost Week 1 Week 2 Week 3 Week 4 Week 5 A $1,000 B $3,000 C $1,500 D $2,500 1. What is ACWP? 2. What is BCWP? 3. What is BCWS