Question: Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items
Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items are routed to a sperate rework station with 2 workers. The rework time is 16 minutes per unit. The process capacity is within
Question 1 options:
Below 8 units per hour
8.1 - 16 units per hour
16.1 – 20 units per hour
20.1 – 24 units per hour
Above 24.1 units per hour
Step by Step Solution
3.47 Rating (163 Votes )
There are 3 Steps involved in it
81 16 units per hour Explanation 1 worker working for 4 minutes produces 1 unit Therefore ... View full answer
Get step-by-step solutions from verified subject matter experts