Consider a single machine flow shop. Schedule the jobs to minimize the total weighted completion time. What is the total weighted completion time? Maximum lateness? (3 + 3 + 2 = 8 marks)
Jobs | 1 | 2 | 3 | 4 | 5 |
Process time pj | 7 | 4 | 6 | 3 | 2 |
Due date dj | 14 | 3 | 7 | 8 | 5 |
Weights wj | 2 | 4 | 5 | 1 | 3 |