Question: Consider a system with five processes P 0 through P 4 and three resources types A , B , C . Resource type A has

Consider a system with five processes P0 through P4 and three resources types A, B, C. Resource type A has 13 instances, type B has 9 instances and type C has 8 instances. Suppose at time t0 following snapshot of the system has been taken.
Process Allocation Max Available
A B C A B C A B C
P0111352434
P1321436
P2111211
P3110122
P4311334
By applying Bankers algorithm
i. What will be the content of need matrix?
ii. Is the system in safe state? If yes, then what is the safe sequence?