Question: Consider a system with five stages. The stages have the process rates of 7 , 4 , 8 , 1 , and 4 1 units

Consider a system with five stages. The stages have the process rates of 7,4,8,1, and 41 units/hour. A product must go through these stages and sequential order. If we double the capacity of all the bottleneck resources, what Will be the new capacity of this process in units/hour?