Question: Consider a variant of the task scheduling problem where each activity has a cost c associated with it and the problem now is to find
Consider a variant of the task scheduling problem where each activity has a
cost c associated with it and the problem now is to find a set of nonconflicting activities such that cost is minimized note that this is different than having the maximum number of activities Show, using a counterexample that the greedy choice of earliest finish time will not yield an optimal solution for this new problem