Question: Consider activity A Create the Foundation depicted in Figure 2 . According to the calculation for estimated time, activity A should have an expected duration

Consider activity A Create the Foundation depicted in Figure 2. According to the calculation for estimated time, activity A should have an expected duration of how many days?
Activity A Time
Activity Optimistic Time Most Likely Time Pessimistic Time
A - Create the Foundation 2 days 5 days 14 days
Group of answer choices
5 days
6 days
7 days