Question: Consider again the below with the normal activity durations, but now suppose the activities require the use of specialized workers. For activities A and G,
Consider again the below with the normal activity durations, but now suppose the activities require the use of specialized workers. For activities A and G, two (2) such workers are needed, while for the other activities, only one (1) such worker is needed. For example, when work is performed on activities D and E, two specialized workers are needed, but three of them are needed to work on F and G.
-
For the normal schedule you found in 3(a), draw a Gantt chart and a resource histogram showing the daily use of specialized workers. How many workers would be needed to complete the project on time?
-
Suppose now only two (2) specialized workers are available to work on this project. Find a new schedule with the earliest project completion date. By how many days is the project delayed due to this resource constraint?
|
| Time (Days) | Cost ($) | ||
| Activity | Normal | Crashed | Normal | Crashed |
| A | 1 |
| 300 | 300 |
| B | 3 | 2 | 1300 | 1700 |
| C | 6 | 4 | 3100 | 3200 |
| D | 10 | 6 | 2100 | 2500 |
| E | 4 |
| 1700 | 1700 |
| F | 3 | 1 | 700 | 750 |
| G | 1 |
| 300 | 300 |
| H | 1 |
| 400 | 400 |