Question: Consider an AS / RS in which an S / R machine is used for each aisle. The length of the storage aisle is 2

Consider an AS/RS in which an S/R machine is used for each aisle.
The length of the storage aisle is 280 ft and its height 46ft.
Suppose horizontal and vertical speeds of the S/R machine are
200 ft/min and 75 ft/min respectively. The S/R machine requires
20sec. to accomplish a P&D operation.
a) Find the single and dual command cycle times per aisle
b) Throughput per aisle under the assumptions that storage system
utilization =90%, and the number of single command and dual
command cycles are equal