Question: Consider an AS / RS in which an S / R machine is used for each aisle. The length of the storage aisle is 2
Consider an ASRS in which an SR machine is used for each aisle.
The length of the storage aisle is ft and its height ft
Suppose horizontal and vertical speeds of the SR machine are
ftmin and ftmin respectively. The SR machine requires
sec to accomplish a P&D operation.
a Find the single and dual command cycle times per aisle
b Throughput per aisle under the assumptions that storage system
utilization and the number of single command and dual
command cycles are equal