Question: Consider consecutive processes A-->B-->C-->D, where process A has a capacity of 27 units per hour. B has a capacity of 0.4 units per minute, C

Consider consecutive processes A-->B-->C-->D,
Consider consecutive processes A-->B-->C-->D, where process A has a capacity of 27 units per hour. B has a capacity of 0.4 units per minute, C has a capacity of 30 units per hour, while process D has a capacity of 0.6 units per minute. According to the Theory of Constraints, where would an operations manager want any inventory? Assume that market demand exceeds available capacity. o In front of process A O In front of process B O In front of process C O In front of process D O After process D