Question: Consider only the cost schedule below of two comparable projects - Assume the cost schedule below is the only thing different between the two projects.
Consider only the cost schedule below of two comparable projects - Assume the cost schedule below is the only thing different between the two projects. - Which project is expected to have a riskier profile? - In other words, which will likely have more variability in the Operating Cash Flows through time?
| A | B | |
| Fixed Costs | $300,000 | $300,000 |
| Variable Costs | $20,000 | $280,000 |
| Total Costs | $320,000 | $580,000 |
Multiple Choice
-
Project A
-
Project B
-
Neither, they both should be the same.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
