Question: Consider PERT and CRM . Which statement is true? Question 2 options: PERT involves crashing activities to compensate for triple constraint issues PERT is an

Consider PERT and CRM. Which statement is true?
Question 2 options:
PERT involves crashing activities to compensate for triple constraint issues
PERT is an acronym that stands for Personal Evaluation Rating Template
Critical path is determined using the PERT method
The arrows that create these diagrams imply meaning based upon the length and direction