Question: Consider projects A and B with the following cash flows: C 0 C 1 C 2 C 3 A $ 35 + $ 19 +
| Consider projects A and B with the following cash flows: |
| C0 | C1 | C2 | C3 | ||||||||||||||
| A | $ | 35 | + | $ | 19 | + | $ | 19 | + | $ | 19 | ||||||
| B | 60 | + | 35 | + | 35 | + | 35 | ||||||||||
| a-1. | What is the NPV of each project if the discount rate is 15%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
| Project | NPV |
| A | $ |
| B | $ |
| a-2. | Which project has the higher NPV? | ||||
|
| b-1. | What is the profitability index of each project? (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
| Project | Profitability index |
| A | |
| B | |