Question: Consider that you are a project manager for a construction project. You are estimating the duration of various activities on this project. The estimated duration
Consider that you are a project manager for a construction project. You are estimating the duration of various activities on this project.
The estimated duration for each activity must be the total elapsed time:
the time for the task plus the time to review and accept the deliverable
the time for the work to be done plus any associated waiting time
all of the given options are correct
the time required for the work times the number of resources assigned to the project
the time for the task plus the planning time for the project