Question: Consider the activities a1, a2, a3, a4, a5, a6 with starting times as {1, 2, 6, 5, 7, 2} and finishing times as {11, 4,

Consider the activities a1, a2, a3, a4, a5, a6 with starting times as {1, 2, 6, 5, 7, 2} and finishing times as {11, 4, 7, 6, 8, 13} consecutively. Use a greedy approach to select a maximum of non-overlapping activities for one single resource.

Selected activities: