Question: Consider the activities and times (in weeks) given for the project below. Crash time represents the shortest amount of time in which an activity can

Consider the activities and times (in weeks)

Consider the activities and times (in weeks) given for the project below. Crash time represents the shortest amount of time in which an activity can be completed. Calculate the crash cost per week for each activity below. (round to a whole number) Preceded by ACTIVITY Normal time Crash time Normal cost $ crash cost $ Crash cost/week A 6 3 8,000 12,000 $/wk B A 7 5 12,000 13,000 $/wk A 6 5 15,000 15,250 $/wk D B,C 4 3 10,000 11,000 $/wk