Question: Consider the activity sequences given in the table given below . a) Draw the network diagram based on the information given below. Calculate the ES,

Consider the activity sequences given in the table given below. a) Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and slack for each activity and identify the critical path. Can the project be completed in 40 weeks?

Activity

Preceding

Activity

Time

(Weeks)

ES EF LS LF Slack
A 10
B 8
C A, B 6
D A 8
E B 9
F C, D 7
G D, E 12
H F, G 10

b) Assume that activity A actually finished at the 9th week, activity B actually finished at the 10th Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!