Question: Consider the all-units quantity discount schedule below. Price Bracket Quantity Ordered Price Per Unit EOQ at that Price 1 1-1999 $100 3,459 2 2000-3999 $90
Consider the all-units quantity discount schedule below.
| Price Bracket | Quantity Ordered | Price Per Unit | EOQ at that Price |
| 1 | 1-1999 | $100 | 3,459 |
| 2 | 2000-3999 | $90 | 3,794 |
| 3 | 4000-5999 | $80 | 3,803 |
| 4 | 6000-7999 | $70 | 4,024 |
| 5 | 8000+ | $60 | 4,647 |
Which of the five price brackets do we know for sure CANNOT contain the optimal order quantity? Answer using the one-digit code from the Price Bracket column.