Question: Consider the analysis of performance data. A control chart is used to: A. Determine if a process is stable. B. Implement a management by objective

Consider the analysis of performance data. A control chart is used to:

A.

Determine if a process is stable.

B.

Implement a management by objective system.

C.

See if a process is capable of meeting its goal objective.

D.

Determine if data from a process varies.