Question: Consider the AON graph of a project shown below . 2 Figure 1 9 . 1 9 The activity times are 3 , 4 ,

Consider the AON graph of a project shown below.2
Figure 19.19
The activity times are 3,4,2,5,7,2,2, and 3 days for activities A1 through A8, respectively. What is the critical path?
A1,A2,A3,A4,A8
A1,A2,A3,A6,A7,A8
A1,A2,A5,A7,A8
None of these options are the critical path
 Consider the AON graph of a project shown below.2 Figure 19.19